veren.
Checklist · Fixes series 02

Go-live checklist: stages, owners, verification and rollback

Write a named person, not a team, into every Owner cell before the cutover starts, then tick each row when its verification passes, not when the work is finished. The progress and the open blockers at the side update as you go, and a blocking row stops the next stage until it passes. Agree the content freeze window and the launch date together before you begin.

AuthorVictor Daj

How to read the columns

  • Owner is a named person, not a team. Fill it in for every row before the first stage starts.
  • Passes when is the verification for the row. The row is done when it passes, not when the work is finished. If a blocking row has no verification you can describe, have the supplier write one before the stage starts.
  • Blocking marks the rows that stop the next stage until they pass. Open blockers are counted at the side.
  • Rollback trigger is the condition that sends the named caller back to the old stack. Fill in each agreed time limit before the switch stage.

Fill it in below. Your result updates as you go.

01Stage 1: preparation (weeks before)

Owner
Passes when
Contact and change lead time written down
Rollback trigger
None
Owner
Passes when
New values confirmed, old values noted
Rollback trigger
None
Owner
Passes when
Checked by a second person against the hosting target
Rollback trigger
None
Owner
Passes when
A test hostname serves with a valid certificate
Rollback trigger
None
Owner
Passes when
Every old URL above the agreed request count has a destination
Rollback trigger
None
Owner
Passes when
Each has an owner and a place in the sequence
Rollback trigger
None
Owner
Passes when
Trigger, caller, return path and return time signed off
Rollback trigger
None

02Stage 2: verification (days before)

Owner
Passes when
Editors confirmed in writing, editing rights reduced
Rollback trigger
None
Owner
Passes when
Agreed sample of pages matches the frozen state
Rollback trigger
None
Owner
Passes when
Every mapped URL lands where expected, no chains
Rollback trigger
None
Owner
Passes when
A test submission arrives, tracking fires
Rollback trigger
None
Owner
Passes when
Each hostname serves the expected brand
Rollback trigger
None
Owner
Passes when
A test record reaches the receiving system
Rollback trigger
None

03Stage 3: switch (the day)

Owner
Passes when
Confirmed by the stage owner
Rollback trigger
None
Owner
Passes when
Change logged with a timestamp
Rollback trigger
Records cannot be activated cleanly
Owner
Passes when
Site served from inside and outside the office
Rollback trigger
Not reachable after the agreed propagation time
Owner
Passes when
All return the expected content or destination
Rollback trigger
Any of the 40 fails
Owner
Passes when
Arrives in the receiving system
Rollback trigger
Not arrived within the agreed time
Owner
Passes when
Announced in writing by the switch owner
Rollback trigger
None

04Stage 4: observation (the window after)

Owner
Passes when
Error rate within the agreed band for the whole window
Rollback trigger
Above the band for longer than the agreed time
Owner
Passes when
Misses added to the map the same day
Rollback trigger
None
Owner
Passes when
New URLs appear in their reporting
Rollback trigger
None
Owner
Passes when
Count within the normal range
Rollback trigger
Enquiries stop entirely
Owner
Passes when
Only after the rollback date has passed
Rollback trigger
None

Rollback position. Fill in before the switch stage and circulate to every owner.

  • What we return to: the old stack on its existing records, kept running until a written date
  • How long the return takes: minutes, with time to live lowered
  • Who may call it: one named person, reachable throughout the switch and observation window
  • What triggers it: the Rollback trigger column above, with each time limit filled in

A launch readiness review, fixed scope, before your next cutover.

It works alongside your existing supplier, so you can run it mid-project without changing who builds the site.

Also in this series
A practical first step